The Koldam Dam Hydropower Project of the NTPC
Limited, commonly known as KolDam, is an embankment
dam on the Sutlej River near Barmana on the
Chandigarh-Manali Highway
( NH-21 ) and the border of Bilaspur district and Mandi
district, Himachal Pradesh, India. The main purpose of the
dam is hydroelectric power generation and it will support
an 800 MW power station.fig: Koldam Dam courtesy: ntpc
The foundation stone for the dam was laid on 5 June 2000 by Prime Minister Atal Bihari Vajpayee. On 14 January 2004, main construction on the dam began. Due to problems associated with habitat and forest loss, the project has been delayed. Attempts to impound the reservoir first failed in December 2013 due to problems with sealing the diversion tunnels. By 18 March 2014, a fourth attempt to seal the tunnels and fill the lake was underway. Repairs were made and another unsuccessful impounding was reached in April 2014 as the diversion tunnels continued to leak. Another period of impounding began on 3 November 2013 and finished on 3 January 2015. A tunnel still leaked though but authorities were confident they would have the power station operational by April. Generator commissioning was originally scheduled for 2009 but was rescheduled to 2015.
Important Details :
Official name
|
Koldam Hydroelectric Power Project
|
Country
|
India
|
Location
|
Bilaspur district and Mandi
district
|
Coordinates
|
31°22′59″N 76°52′16″E Coordinates: 31°22′59″N 76°52′16″E
|
Status
|
Operational
|
Construction began
|
2000
|
Opening date
|
2015
|
Owner(s)
|
National Thermal Power Corporation
|
Dam and spillways
|
|
Type of dam
|
Embankment, rock-fill with clay core
|
Height (foundation)
|
167 m (548 ft)
|
Height (thalweg)
|
153 m (502 ft)
|
Length
|
474 m (1,555 ft)
|
Elevation at crest
|
648 m (2,126 ft)
|
Width (crest)
|
14 m (46 ft)
|
Dam volume
|
12,000,000 m3(15,695,407 cu yd)
|
Spillway type
|
Chute, six radial
gates
|
Spillway capacity
|
16,500 m3/s (582,692 cu ft/s)
|
Reservoir
|
|
Total capacity
|
560,000,000 m3(453,999 acre·ft)
|
Max. length
|
40 km (25 mi)
|
Normal elevation
|
642 m (2,106 ft)
|
Power station
|
|
Commission date
|
2015
|
Hydraulic head
|
144 m (472 ft) (static)
|
Turbines
|
4 x 200 MW Francis-type
|
Installed capacity
|
800 MW
|
Power Generation Capacity
Its installed capacity is of 800 MW (4x200 MW). The first
200 MW Francis turbine-generator was commissioned on 30
March 2015 and the third on 10 April 2015.
Unit Number
|
Capacity (MW)
|
Date of Commissioning
|
Status
|
1
|
200
|
2015 Mar
|
commissioned.
|
2
|
200
|
2015 April
|
commissioned
|
3
|
200
|
2015 April
|
commissioned
|
4
|
200
|
2015 June
|
commissioned
|
TOTAL
|
800
|
No comments:
Post a Comment